Home / Component Range / Industrial Battery Testers / Industrial Battery Tester Accessories / Tekon Battery Tester PLASTIC Plug Probe Lead Set
SKU: BT19127
A replacement probe lead set for Tekon battery testers. Keep a spare set on hand so field battery testing is not held up by worn or damaged leads. It suits maintenance teams carrying out routine battery testing on standby and backup power systems. Check that your Tekon tester model matches before ordering. This probe set comes with a Plastic Plug
Also available with a Metal Plug. See Product BT19128.

| SKU | BT19127 |
|---|---|
| Box Quantity | 1 |
Three tiers. Impedance or conductance testing (instruments such as impedance meters) is fast, done on a live circuit, and reliably detects open cells, dry-out and connection degradation, but requires a baseline from when the bank…
Full answer: What battery testing methods are recommended?
Yes, and this is where most monitoring vendors overclaim. Impedance and conductance are trend indicators, not capacity measurements. They catch open cells, dry-out and connection faults, and rising impedance correlates with capacity fade, but the…
Full answer: Do I still need discharge testing if I have monitoring?
AS 2676 covers installation, maintenance, testing and replacement of secondary batteries in buildings, in two parts (vented and sealed cells). It is the standard Australian asset owners are audited against, and it is the correct…
Full answer: What does AS 2676 require for battery maintenance and testing?
The usual convention is that a battery bank has reached end of life when it can deliver only 80% of its rated capacity. Below that point it can no longer be relied on to give…
Full answer: How do I know when to replace a battery bank?
This is the real problem. AusNet says full discharge and discharge-rate testing are “impractical on zone substations with a single battery bank”, which “prevent[s] accurate measurement of the DC system available capacity.” AusNet’s response is…
Full answer: How do I assess capacity on a single-bank zone substation where a discharge test is impractical?
An account is required to add products to your cart, please login or register for an account.