How do I reduce diesel dependence at a remote site?

Change what the generator is for.

A diesel-only site runs its generator all the time against a changing load. It spends most of its life lightly loaded, which is where it is least efficient and where wet stacking and maintenance problems start.

A solar hybrid system runs the load from solar and battery storage. The generator only starts to recharge the batteries, at high load, for a set period.

The measure to hold a supplier to is generator run hours per week. Run hours drive fuel, servicing and refuelling trips together. We model expected consumption and renewable fraction in our proposals rather than quoting a percentage.

More questions on this topic

Fix the enclosure before the battery. VRLA loses roughly 50% of its life for every 10 °C sustained above 20 °C, and heat damage cannot be reversed.

In order of effect:

  1. Measure the temperature inside the enclosure in summer, at the terminals, not the outside air.
  2. Specify temperature-compensated charging. This is essential in an uncontrolled environment.
  3. Improve the enclosure with shading, ventilation, a heat-reflective finish or a double skin.
  4. Then choose the chemistry. LiFePO₄ is preferred where the site truly runs hot, because it does not follow the lead acid temperature and life curve.

Less than most people expect, which is why a small pre-engineered system like ModX1 is usually the right fit.

Typical measured continuous loads:

  • SCADA, RTU and telemetry panels: 80–280 W
  • Communications, GRN and PSN repeaters: 100–200 W
  • Cameras and access control: 50–150 W

At those loads, a 5–15 kWh storage system with a modest solar array gives days of autonomy.

Before you enquire, measure the actual 24-hour consumption. Adding up nameplate ratings usually overstates the real load by a wide margin and leads to a system twice the size it needs to be.

Yes. A towable stand-alone power system like V-Trail is built for it:

  • deploys in minutes rather than days
  • needs no civil works
  • runs on solar, with a diesel generator as backup
  • can be recovered and moved to the next location

For a shutdown, that means temporary power that arrives before the contractors do. For exploration, the same unit serves each drill program in turn.

The real limits are vehicle access to the site and having the unit staged and ready. A deployable unit ordered only when it is needed is not a deployable unit.

Mostly through reduced manual handling and fewer site visits. Manual handling of large lead-acid monoblocs is a recognised musculoskeletal injury exposure for maintenance crews, and a lithium bank of equivalent usable energy is a fraction of the weight and volume. Front terminal formats remove reaching across live terminals on upper tiers. And maintenance-free or very-low-maintenance systems with remote monitoring cut the number of trips to remote and difficult-to-access locations, which removes driving exposure, usually the largest single risk in remote site work. Note that where hazardous-area or Ex requirements apply, that is a separate specification conversation to have early.

A structured programme rather than an inspection habit. A register of installed batteries with date codes captured at installation. Condition testing on a schedule, impedance trending as the routine tool, with a capacity test at a defined interval or when the trend crosses a threshold, remembering that impedance indicates trend rather than measuring capacity. State of charge and health visibility through monitoring, so that the schedule can shift from calendar-based to condition-based and the number of trips falls. And planned replacement on a defensible age or condition policy rather than on failure. The saving on a remote fleet is almost never in the batteries; it is in converting emergency callouts into scheduled work. —

Enquire Now

Login Required

An account is required to add products to your cart, please login or register for an account.