On-site electrical work is measured in hours rather than days. The system is factory integrated, pre-wired and tested before it leaves our facility, so there is no field integration to do. Installers have reported install-time savings of up to 70% against building an equivalent system from components.
A field-built equivalent typically occupies one or two licensed electrical workers for two to five days across mounting, wiring, controller configuration and troubleshooting.
The larger schedule item is usually not installation labour at all. It is structural certification, which runs 6 to 12 weeks and sits on the critical path before anyone can go to site. A pre-engineered platform removes that from the schedule, because the certification already exists.
Where site access is the constraint rather than labour, a possession window, a shutdown, a wet-season deadline, a compliance date, that schedule compression is generally the reason customers choose this platform over building their own.