It is set by criticality and restoration time, not by convention, but Australian specifications give real benchmarks worth quoting:

Application

Published requirement

Rail, active level crossing

48 hours with 10% residual capacity (ARTC ESC-03-01)

Substation DC, system black duty

10 hours (AusNet AMS 20-80)

Mobile base station, hardened

At least 12 hours (Commonwealth Mobile Network Hardening Program)

Traffic signals / ITS roadside

4 hours at full load (TMR MRTS213; NZTA 1–8 h site-determined)

HV water utility installation

4 hours minimum (Sydney Water DOC0008)

Stand-alone power system

2 days with auto generator, 4–5 days without (AS/NZS 4509.2)

Nobody else has these numbers assembled in one place, and each maps to a Valen product line.