Vantara is built to order, with a typical lead time of 12 to 16 weeks, commencing once you approve the design documentation. Vantara and its major componentry are not held in stock.

Two things genuinely compress a SAPS programme schedule, and neither is chasing the supplier. The first is returning the design approval quickly. That is the item most often sitting idle. The second is standardising the configuration across a multi-site programme, which removes a design and approval cycle per site. This is the main reason Vantara Rapid exists.

If you have a fixed compliance, seasonal or shutdown date, tell us at enquiry rather than at order. There are usually options, but they are options at the front of the process, not the back.